Free Beta: Procurement discovery is free; verify every opportunity on SAM.gov. Source status
Bid opportunityClosing soon

Trimax Upgrade

DEPT OF DEFENSE › DEPT OF THE AIR FORCE › FA9302 AFTC PZZ

Response deadlineAug 24, 2026 3:00 PM EDT
View official notice on SAM.gov (opens in a new tab)
Verify before acting. Users must verify deadlines, amendments, attachments, eligibility, and submission requirements on the official SAM.gov notice. Read the Data Disclaimer.

Key decision factors

Response deadline
Aug 24, 2026 3:00 PM EDT
Posted
Aug 18, 2026 12:00 AM EDT
Notice type
Combined Synopsis/Solicitation
Set-aside
No Set aside used
NAICS
541330
PSC
R425
Place of performance
Edwards, California
Current status
Closing soon

Notice details

Official status
Closing soon
Normalized group
Bid opportunity
Notice ID
8e45402e320e456bb6c3343bf840c2c1
Solicitation number
FA930226Q0110

Description

Displayed as sanitized plain text from SAM.gov. Retrieved Aug 19, 2026 8:09 PM EDT.

Combined Solicitation & Notice of Intent (SOLE SOURCE) This is a combined synopsis/solicitation for commercial products and commercial services prepared in accordance with RFO Part 12. This announcement constitutes the only solicitation. Offers are being requested and a separate, written solicitation will not be issued [RFO12.202(b)(1)] (i) AFTC/PZZG intends to negotiate on a Sole Source basis with Trimax Systems, LLC for engineering and system integration services to modernize B1030’s Electrical, Gas, and Water (EGW) control infrastructure. The existing EGW control system at Building 1030 was originally engineered and programmed by Trimax and relies entirely on their proprietary Programmable Logic Controller (PLC) and Human-Machine Interface (HMI) source code. Solicitation number FA930226Q0110 is issued as a request for quotation (RFQ). This acquisition is not set aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov. (ii) SCOPE OF WORK: System Engineering and Programming PLC Logic Development: The contractor shall engineer and program the Programmable Logic Controllers (PLCs) to accurately control the designated facility equipment (e.g., pumps, valves, and generators) in accordance with the approved sequence of operations. HMI/SCADA Configuration: The contractor shall develop and deploy the Human- Machine Interface (HMI) screens. The graphical interface must provide operators with real-time equipment status, historical data trending, and immediate visual/audible alarming for critical system faults. Cybersecurity & Compliance: All software configurations and network integration shall adhere to current Risk Management Framework (RMF) guidelines. The contractor must ensure that default passwords are changed, unnecessary ports are disabled, and role-based access controls are implemented. Installation and Hardware Integration Panel Assembly: The contractor shall assemble, wire, and label all internal components of the control panels prior to site delivery. All wiring must be clearly labeled and correspond directly to the provided schematic drawings. On-Site Implementation: The contractor shall physically install the upgraded components, terminate field wiring, and establish network connectivity without causing uncoordinated disruptions to ongoing facility operations. Testing and Commissioning Site Acceptance Testing (SAT): Following installation, the contractor shall conduct a comprehensive SAT alongside government representatives. This includes point-to-point loop checks, verification of all automated sequences, and simulated fault testing to ensure alarms trigger correctly. System Cut-Over: The contractor shall manage the transition from the legacy system to the new system, ensuring continuous utility support during the cut-over phase (iii) See attached redacted Sole Source Justification that supports only one source is available to provide these services. (iv) FOB Destination, Building 1030, Edwards Air Force Base (EAFB). PoP is estimated at 30 days. (v) See attached SF1449 for a list of solicitation provisions that apply to the acquisition. (vi) See attached SF1449 for a list of contract clauses that apply to this acquisition. (vii) If you have any questions, please contact Contract Specialist, Carmen Barahona at carmen.barahona@us.af.mil, or Contracting Officer Karla Vazquez at karla_lizette.vazquez_montes@us.af.mil. Response times. This letter does not constitute a change order, nor does it grant permission to begin work on the proposed requirements. It is requested that your proposal be submitted as soon as practical, but no later than 12PM PDT on 24 August 2026 to allow for analysis and processing. NOTICE OF INTENT TO SOLE SOURCE Justification Trimax Systems, LLC is the only responsible source capable of fulfilling the 772nd Test Squadron's (772TS/EWOX) requirement because the existing Electrical, Gas, and Water (EGW) control system at Building 1030, Edwards Air Force Base (EAFB), was originally engineered and programmed by Trimax and relies entirely on their proprietary Programmable Logic Controller (PLC) and Human-Machine Interface (HMI) source code. Although the Government received interest from five vendors during the sources sought phase, they were determined technically unacceptable because they do not possess, and cannot legally obtain, the proprietary Trimax PLC/HMI source code required to perform the upgrades without a total system replacement. Utilizing an alternate vendor would require a complete, ground-up reverse-engineering of the entire utility control network, resulting in a duplication of costs up to $500,000 that the Government is not expected to recover through competition. Additionally, this would cause an unacceptable mission delay due to prolonged facility utility shutdowns of 6 to 8 months required to engineer, install, test, and deploy a new system. Trimax retains proprietary rights and interests in this customized software, programming, configurations, engineering methods, and related intellectual property, except to the extent that specific rights may have been expressly conveyed under an applicable contract or other written agreement. The underlying PLC and HMI manufacturers' software, development environments, firmware, and other third-party components remain subject to the respective manufacturers' intellectual property rights and license terms. The existing control system incorporates Trimax-developed application code and configurations as well as third-party software and development tools that may be subject to manufacturer licensing requirements. Modification by a third-party integrator would therefore require appropriate software licenses, authorized development tools, access credentials, source files, technical knowledge of the existing Trimax implementation, and explicit authorization to use or modify Trimax proprietary intellectual property. In addition, modifications to the existing PLC and HMI applications by parties other than Trimax may affect system functionality, operability, cybersecurity, safety, reliability, future support, and Trimax's ability to warrant or assume responsibility for the performance of the modified system. Therefore, to preserve the system's technical integrity, avoid unnecessary and non-recoverable Government expenditures, and prevent critical mission downtime, Trimax Systems, LLC is the only source that can perform these integration services. Scope of Work See attached SOW or Section (ii) above. Market Research Contracting posted a Sources Sought on SAM.gov from 13 July 2026 through 16 July 2026 and received 5 timely responses. The responses were sent to Mission Partner but deemed technically unacceptable because they do not possess, and cannot legally obtain, the proprietary Trimax PLC/HMI source code required to perform the upgrades without a total system replacement. Lastly, Contracting obtained documentation from Trimax confirming the proprietary nature of their Programmable Logic Controller (PLC) and Human-Machine Interface (HMI) source code. Instructions to Interested Parties This notice of intent is not a request for competitive proposals; however, all responsible sources may submit a capability statement, proposal, or quotation which shall be considered by the agency. A determination by the Government not to compete this proposed contract based upon responses to this notice is solely within the discretion of the Government. Information received will normally be considered solely for the purpose of determining whether to conduct a competitive procurement.

Attachments

5 attachments reported by SAM.gov

Files are hosted by SAM.gov. Open the official notice to review and download them.

View attachments on SAM.gov (opens in a new tab)

Contacts

Carmen Barahona
Primary
carmen.barahona@us.af.mil

Personalized relevance

Would this fit your company?

Create company profile information with a free account to see a deterministic, explainable relevance score. Matching does not determine eligibility or win probability.

Create Free Account

Pursuit risk (separate from your match score)

Strong pursuit warning

This notice contains language indicating a sole-source or otherwise restricted procurement. Review the cited evidence before investing time in a response.

Detected in

  • Description“Combined Solicitation & Notice of Intent (SOLE SOURCE) This is a combined synopsis/solicitation for commercial products and commercial services prepared in accordance with RFO Part 12. This announcement constitutes the o”
  • Description“ore, to preserve the system's technical integrity, avoid unnecessary and non-recoverable Government expenditures, and prevent critical mission downtime, Trimax Systems, LLC is the only source that can perform these integ”
  • Description“ments. It is requested that your proposal be submitted as soon as practical, but no later than 12PM PDT on 24 August 2026 to allow for analysis and processing. NOTICE OF INTENT TO SOLE SOURCE Justification Trimax Systems”
  • Description“ical, Gas, and Water (EGW) control infrastructure. The existing EGW control system at Building 1030 was originally engineered and programmed by Trimax and relies entirely on their proprietary Programmable Logic Controlle”

Pursuit risk is evaluated separately from your match score above and never changes it. This is not a legal or eligibility determination — verify against the official SAM.gov notice and attachments.